Second storey addition power in Parramatta: what happens to your supply when you build up

What happens to the service line, raiser and mains when you add a second storey to a Parramatta home, and how to plan it with your builder.

Get a free quote

Takes a minute. We'll call you back, usually the same day.

No obligation. Your details stay with us and are never sold or shared.

Going up instead of out is popular across Parramatta. Single-storey brick homes in Ermington, Rydalmere, Carlingford and Toongabbie sit on decent blocks, and a second storey adds space without losing the yard. What many owners don’t plan for is the service line. It’s attached to the house at a point that suited a single-storey roof, and once the new level goes up, that point is usually in the wrong place. This guide explains second storey addition power so it doesn’t surprise you mid-build.

Why the supply has to change

Your service line attaches to the house at a raiser above the roof or a bracket on the wall. When a second storey goes on:

  • The raiser may end up inside the new walls or under the new roof
  • The bracket may be too low or in the way of new windows
  • The line may not clear the new structure by the required distances
  • Scaffolding and cranes need to stay clear of a live line

So the attachment point has to move, or the supply goes underground.

Option 1: Move the attachment point

We fit a new raiser or bracket on the new structure, at a height and position that meets the clearance rules. This is a point of attachment upgrade. It’s the simplest option when the street is overhead and the line can reach the new position cleanly.

Option 2: Go underground

An overhead to underground conversion removes the line and raiser altogether. The cable runs in conduit from the street pole to the meter board. It suits second storeys well: no raiser on the new facade, no clearance issues and no line in the way of the builders.

The mains

If the cable from the attachment point to the meter board is old, replace it at the same time with a consumer mains upgrade. A bigger home often has a bigger load too: more air conditioning, more bathrooms, sometimes an EV charger.

During the build

There’s usually a stage where the supply has to be isolated or temporarily re-routed while the old roof comes off and the new frame goes up. We plan this with your builder using a power disconnection and reconnection at the right moments. Many families stay in the house, with short planned outages.

Timing

  1. Design stage. Tell your designer where the supply will go so the new facade allows for it.
  2. Before the roof comes off. Isolate or re-route the line as needed.
  3. Frame up. Install the new attachment point or underground conduit.
  4. Before lining. Run new mains inside if needed.
  5. Near completion. Final connection, test and certificate.

Heritage considerations

On Federation cottages in Harris Park and North Parramatta, second storeys are often set back to protect the street view. The supply can be planned to stay out of sight on the facade as well.

Costs

Costs depend on whether you move the raiser or go underground, the length of the run, and whether new mains are needed. We give a fixed price for each stage once we’ve seen the plans.

Questions to ask your builder

  • Has the service line been allowed for in the program?
  • Who’s booking the network isolation?
  • Will the line clear the scaffolding?
  • Where will the meter board end up?

Mistakes we see

Leaving it to the end. The frame goes up around a live raiser and the builder has to stop while the supply is sorted.

Forgetting clearances. A new balcony or window ends up within reach of the service line, and the line has to move again.

Keeping old mains. The house doubles in size but still runs on cable from the 1970s, and the main switch trips the first summer.

No conduit for the future. A second storey is often the moment owners add an EV charger later. Laying conduit sized for three phase now costs little.

Ausgrid or Endeavour

Most Parramatta homes are on Endeavour Energy. Some homes on the eastern edge, around Epping, are on Ausgrid. The process is similar, and we’re accredited with both, so you don’t need to work out which applies.

Staying in the house

Many Parramatta families live at home through a second storey build. That’s usually fine for the power side. Outages for the supply work are planned, short and booked ahead, so you can work around them.

Temporary supply during the build

On bigger additions, where the roof is open for weeks, the builder may want a separate site supply for the trades while the house is isolated. We can set one up beside the house and remove it at the end.

Getting help

Call the Parramatta level 2 electrician team with your plans. We’ll recommend the best option and coordinate with your builder. If you’re knocking down and building a duplex instead, read our guide to duplex power connection.

Updated

Second storey addition power in Parramatta: common questions

Something else on your mind? Call 02 9158 9915 and ask.

Will we be without power during the build?

Usually only for short periods. Many families stay in the house, with planned outages for the supply work.

Should we go underground instead of moving the raiser?

Often, yes. It avoids a tall raiser and keeps the new facade clean.

Who books the network work?

We do. Your builder just needs to tell us the program.